Preparing and building the foundation

  • Concrete Preparation: Diamond grind the surface to ensure proper adhesion.

  • Primer or Moisture Vapor Barrier (if needed): Applied to address moisture concerns and create a solid base.

  • Base Coat Application: Lay the base coat in the color of your choice.

  • Flake or Metallic Highlights: Add decorative flakes or metallic accents, depending on the floor type.

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram
worker-working-on-the-floor-of-an-industrial-build-2023-11-27-05-26-39-utc (1).jpg
polishing-machine-with-soft-disc-on-epoxy-table-cl-2023-11-27-05-05-37-utc (1).jpg

Second Day

Finishing and perfecting the floor

  • Surface Refinement:

    • Sand the top coat to remove blemishes and bubbles (for metallic floors).

    • Scrape excess flake for a smooth finish (for flake floors).

  • Top Coat Application: Apply a durable polyaspartic top coat to seal and protect the floor.

  • Drying Time: Allow 24 hours for walking and 72 hours for driving to ensure proper curing.